The following are the results of bids received October, 2018 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed.  The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.

NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
 

 View Project Details for this Bid Letting




HENRY -- PROJECT # 18-06-44-02                10/18/2018                Large Project Letting
LAKE GEODE
VALVE REPLACEMENT PLAN
 
BIDS RECEIVED:
    Engineering & Construction Innovations, Inc. 
$157,900.00 
    Miller Trucking & Excavating 
$225,900.00 
    Meyers Driveway 
$263,200.00 
    Carl A Nelson & Co 
$305,239.00 
    Minturn Inc 
$329,200.00 


full bid tab




POLK -- PROJECT # 18-02-77-01                10/18/2018                Large Project Letting
BIG CREEK STATE PARK
JETTY REPAIRS
 
BIDS RECEIVED:
    Dingman Construction 
$136,991.00 
    JNC Construction, LLC 
$145,760.25 
    Richards Construction Co., Inc. 
$155,529.50 
    Michael J Lamb dba Lamb Tiling 
$157,020.25 
    TK Concrete, Inc. 
$160,243.00 
    Gehrke Inc. 
$170,460.25 
    RW Excavating Solutions LC 
$179,230.40 
    Niewohner Construction Inc. 
$192,425.00 
    J & K Contracting 
$195,195.00 
    Jasper Construction Services, Inc. 
$204,890.00 

The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.
   Con-Struct, Inc.

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.


full bid tab




WRIGHT -- PROJECT # 18-02-99-01                10/11/2018                Small Project Letting
ELM LAKE WMA
WETLAND RESTORATION
 
BIDS RECEIVED:
    Richards Construction Co., Inc. 
$32,960.00 


full bid tab




DICKINSON -- PROJECT # 18-01-30-06                10/25/2018                Small Project Letting
GULL POINT STATE PARK
ENTRY PORTAL REPAIR (D1FY19-10)
 
BIDS RECEIVED:
    Midstates Builders, Inc. 
$19,198.00 
    Under Construction 
$41,730.00 
    Wilcon Construction, Inc. 
$48,380.00 


full bid tab