The following are the results of bids received June, 2015 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| MARION -- PROJECT # 15-05-63-02 6/18/2015 Large Project Letting
| ELK ROCK STATE PARK
| SHORELINE ARMORING | | BIDS RECEIVED: |
Strand Excavating Inc.
|
$248,200.00 |
Hammes Bulldozing Inc.
|
$249,500.00 |
Cole Construction Company Inc
|
$262,850.00 |
RW Excavating & Dozing
|
$281,655.00 |
Legacy Corporation of Illinois
|
$302,500.00 |
Niewohner Construction Inc.
|
$313,730.00 |
Superior Seawalls & Docks
|
$355,090.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. TK Concrete Inc
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.
|
| RINGGOLD -- PROJECT # 15-04-80-01 6/18/2015 Large Project Letting
| MOUNT AYR FISHERIES MANAGEMENT UNIT
| WALNUT CREEK MARSH RESTORATION | | BIDS RECEIVED: |
Kevin Kent Construction
|
$116,335.00 |
Jeff Sickels Doziing LLC
|
$129,190.00 |
TEK Builders, Inc.
|
$140,654.00 |
|
| WEBSTER -- PROJECT # 15-02-94-10 6/18/2015 Large Project Letting
| DOLLIVER MEMORIAL
| PARK RESIDENCE IMPROVEMENTS | | BIDS RECEIVED: |
Jensen Builders LTD
|
$132,200.00 |
Pronghorn Group LLC
|
$141,516.00 |
|
| DICKINSON -- PROJECT # 14-01-30-06 6/4/2015 Small Project Letting
| CENTER LAKE
| CENTER LAKE ROCK FISH BARRIERS | | BIDS RECEIVED: |
Valley Contracting Inc.
|
$21,830.00 |
Diamond Concrete & Construction, Inc.
|
$23,950.00 |
Jeppesen Gravel
|
$26,520.00 |
|
| FRANKLIN -- PROJECT # 15-02-35-01 6/11/2015 Small Project Letting
| BEED'S LAKE
| LODGE AND SHELTER RESTORATION | | BIDS RECEIVED: |
M.D. Johnson Consulting, LLC
|
$49,800.00 |
|
| MILLS -- PROJECT # 15-04-65-01 6/11/2015 Small Project Letting
| OTHER
| HUTCHINGS CANOE ACCESS | | BIDS RECEIVED: |
Hymbaugh Construction
|
$35,160.00 |
Carley Construction LLC
|
$46,722.50 |
|
| MILLS -- PROJECT # 15-04-65-02 6/11/2015 Small Project Letting
| OTHER
| NEW RIVER ACCESS WITH PARKING | | BIDS RECEIVED: |
Hymbaugh Construction
|
$35,016.00 |
Carley Construction LLC
|
$50,052.00 |
|
| POLK -- PROJECT # 15-05-77-9 6/11/2015 Small Project Letting
| STATE FAIR BUILDING
| ELECTRICAL CONDUIT | | BIDS RECEIVED: |
ABC Electrical Services, LLC
|
$18,800.00 |
|
| JASPER -- PROJECT # 15-05-50-02 6/18/2015 Small Project Letting
| ROCK CREEK STATE PARK
| BOAT RAMP REPLACEMENT | | BIDS RECEIVED: |
Strand Excavating Inc
|
$45,901.00 |
Boulder Contracting, LLC
|
$57,052.00 |
Cushman Excavation
|
$86,080.05 |
|
| MUSCATINE -- PROJECT # 13-06-70-01 6/18/2015 Small Project Letting
| FAIRPORT FISH HATCHERY
| SEAL PONDS 23, 25, 26 ,& 30 | | BIDS RECEIVED: |
CAJ Enterprises Inc. dba Chris Jones Trucking
|
$11,143.00 |
Triple B Construction Corporation
|
$11,800.00 |
|
|