BID LETTING RESULTS - May, 2018

 
 

The following are the results of bids received May, 2018 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed.  The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.

NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
 

 View Project Details for this Bid Letting




ADAIR -- PROJECT # 18-04-01-01                5/24/2018                Large Project Letting
MIDDLE RIVER FOREST AREA
MIDDLE RIVER FOREST PARK ACCESS
 
BIDS RECEIVED:
    JNC Construction, LLC 
$43,016.74 
    Dingman Construction 
$58,301.46 
    Michael J. Lamb DBA Lamb Tiling 
$69,141.00 
    Caliber Concrete LLC 
$73,754.50 
    Nelson & Rock Contracting, Inc. 
$78,040.00 
    TEK Builders, Inc. 
$105,096.00 


full bid tab




ALLAMAKEE -- PROJECT # 18-03-03-02                5/24/2018                Large Project Letting
VILLAGE CREEK ACCESS AT LANSING, IOWA
PARKING LOT PAVING AND BOAT RAMP EXTENSIONS
 
BIDS RECEIVED:
    Wicks Construction Inc. 
$910,220.60 
    Skyline Construction Inc. 
$947,999.99 
    Croell, Inc. 
$1,032,606.30 
    CDMI Concrete Contractors Inc. 
$1,036,852.00 


full bid tab




BUENA VISTA -- PROJECT # 18-01-11-02                5/24/2018                Large Project Letting
STORM LAKE
PHASE II ISLAND STABILIZATION
 
BIDS RECEIVED:
    Shekar Engineering, P.L.C. 
$389,025.00 
    Niewohner Construction Inc. 
$445,985.00 
    Peterson Contractors, Inc. 
$455,640.00 
    Dubuque Barge & Fleeting Service dba Newt Marine 
$457,350.00 
    Superior Seawalls, Inc. 
$548,850.00 

The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.
   Water Works Docks and Boatlifts Inc.

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.


full bid tab




MONTGOMERY -- PROJECT # 18-04-69-01                5/24/2018                Large Project Letting
VIKING LAKE
SEAWALL REPLACEMENT
 
BIDS RECEIVED:
    Water Works Docks and Boatlifts Inc. 
$192,376.96 
    Niewohner Construction Inc. 
$194,274.00 
    Nelson & Rock Contracting Inc. 
$195,095.60 
    Superior Seawalls, Inc. 
$267,028.60 
    Dixon Construction Co. 
$293,190.00 
    TEK Builder, LLC 
$304,043.65 
    Miller Trucking & Excavating 
$307,725.00 
    Building Crafts, Inc. 
$317,450.00 
    Dubuque Barge & Fleeting Service dba Newt Marine 
$319,558.00 


full bid tab




STORY -- PROJECT # 16-02-85-03                5/24/2018                Large Project Letting
HICKORY GROVE LAKE
LOW WATER DRAIN PIPE AND VALVE
 
BIDS RECEIVED:
    Gehrke, Inc. 
$849,585.00 
    Minturn, Inc. 
$1,024,025.00 
    Peterson Contractors, Inc. 
$1,045,697.50 


full bid tab




FRANKLIN -- PROJECT # 17-02-35-01                5/31/2018                Large Project Letting
BEED'S LAKE STATE PARK
ROAD REPAIR
 
BIDS RECEIVED:
    Heartland Asphalt, Inc. 
$202,657.10 


full bid tab




FREMONT -- PROJECT # 17-04-36-01                5/31/2018                Large Project Letting
WAUBONSIE STATE PARK
PAVEMENT MAINTENANCE
 
BIDS RECEIVED:
    Midwest Coatings Company, Inc. 
$246,310.50 


full bid tab




JASPER -- PROJECT # 17-05-50-01                5/31/2018                Large Project Letting
ROCK CREEK STATE PARK
PAVEMENT MAINTENANCE
 
BIDS RECEIVED:
    Manatts Inc 
$348,719.55 


full bid tab




POTTAWATTAMIE -- PROJECT # 17-04-78-05                5/31/2018                Large Project Letting
WILSON ISLAND STATE RECREATION AREA
PAVEMENT REPAIR
 
BIDS RECEIVED:
    Midwest Coatings Company, Inc. 
$281,083.50 


full bid tab




APPANOOSE -- PROJECT # 18-05-04-05                5/3/2018                Small Project Letting
RATHBUN FISH HATCHERY RESEARCH BUILDING
ELECTRIC FOR FISH CULTURE SYSTEMS
 
BIDS RECEIVED:
    Superior Cable & Data LLC 
$44,666.00 


full bid tab




CERRO GORDO -- PROJECT # 18-03-17-02                5/3/2018                Small Project Letting
CLEAR LAKE PONDS WMA
MODIFY WATER CONTROL STRUCTURE
 
BIDS RECEIVED:
    Larson Contracting Central, LLC 
$16,280.00 


full bid tab




JOHNSON -- PROJECT # 18-06-52-04                5/3/2018                Small Project Letting
LAKE MACBRIDE STATE PARK
AIR CONDITIONER REPLACEMENT
 
BIDS RECEIVED:
    Sound Mind Real Estate, LLC 
$13,754.32 
    JP Plumbing & Heating, Inc. 
$14,400.00 


full bid tab




LUCAS -- PROJECT # 18-05-59-01                5/3/2018                Small Project Letting
STEPHENS FOREST HEADQUARTERS
DRIVEWAY REPLACEMENT
 
BIDS RECEIVED:
    Wright Build 
$9,657.00 
    Day Construction Services LLC 
$9,672.00 
    Mcgee Concrete, LLC 
$10,050.85 
    Hymbaugh Construction 
$10,580.00 
    TK Concrete, Inc. 
$10,925.00 


full bid tab




WASHINGTON -- PROJECT # 18-06-92-03                5/9/2018                Small Project Letting
LAKE DARLING STATE PARK
D4FY19-1 TRAIL REPAIR AT BRIDGE
 
BIDS RECEIVED:
    DeLong Construction Inc 
$9,380.00 


full bid tab




WORTH -- PROJECT # 17-03-98-03                5/10/2018                Small Project Letting
RICE LAKE WMA
REPAIR FLOOD DAMAGED DIKE & WATER CONTROL STRUCTURE
 
BIDS RECEIVED:
    A1 Excavating & Drainage Inc. 
$12,850.00 
    Burr Oak Springs 
$16,905.00 
    Rognes Bros. Excavating, Inc. 
$19,550.00 
    Larson Contracting Central, LLC 
$24,435.00 
    Cole Excavating, LLC 
$27,100.00 


full bid tab




DICKINSON -- PROJECT # 17-01-30-02                5/17/2018                Small Project Letting
GULL POINT STATE PARK
GULL POINT RESIDENCE WINDOW & DOOR REPLACEMENT
 
BIDS RECEIVED:
    Wilcon Construction, Inc. 
$57,055.00 
    Midstates Builder, Inc. 
$67,596.00 


full bid tab




DICKINSON -- PROJECT # 17-01-30-02                5/17/2018                Small Project Letting
GULL POINT STATE PARK
GULL POINT RESIDENCE WINDOW & DOOR REPLACEMENT
 
BIDS RECEIVED:
    Wilcon Construction, Inc 
$42,598.00 
    Midstates Builder, Inc. 
$58,912.00 


full bid tab




CASS -- PROJECT # 19-04-15-01                5/24/2018                Small Project Letting
LAKE ANITA
SHORELINE RIP-RAP
 
BIDS RECEIVED:
    JNC Construction, LLC 
$14,791.60 
    Lamb Tiling 
$17,060.00 


full bid tab