BID LETTING RESULTS - January, 2021

 
 

The following are the results of bids received January, 2021 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed.  The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.

NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
 

 View Project Details for this Bid Letting




ADAMS -- PROJECT # 17-04-02-01                1/21/2021                Large Project Letting
LAKE ICARIA
PAVEMENT PRESERVATION
 
BIDS RECEIVED:
    Blacktop Service Co 
$449,223.46 


full bid tab




HENRY -- PROJECT # 18-06-44-03                1/21/2021                Large Project Letting
GEODE STATE PARK
SHORELINE ARMORING
 
BIDS RECEIVED:
    Water Works Docks & Boat Lifts, Inc. 
$344,900.00 
    Miller Trucking & Excavating 
$497,291.00 
    Superior Seawalls Inc 
$528,626.50 
    Langman Construction Inc 
$543,852.00 
    Legacy Corporation of IL 
$568,770.00 
    Cole Construction Co Inc 
$573,604.15 
    Newt Marine Service 
$574,977.35 
    Four Seasons Excavation, Inc. 
$616,120.00 
    Brandt Construction Co. 
$674,510.00 
    Veit & Company, Inc. 
$679,486.00 

The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.
   CAJ Enterprises, Inc dba Chris Jones Trucking

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.


full bid tab




FREMONT -- PROJECT # 20-04-36-04                1/21/2021                Small Project Letting
RIVERTON WMA
OVERLOOK DECK
 
BIDS RECEIVED:
    United Construction Services  
$49,025.20 
    Vieco Development & Construction Co. Inc. 
$62,275.00 
    Pillar Inc. 
$81,356.77 


full bid tab




WINNEBAGO -- PROJECT # 21-02-95-01                1/28/2021                Small Project Letting
CLEAR LAKE WILDLIFE UNIT
HARMON LAKE - EAST WCS REPLACEMENT
 
BIDS RECEIVED:
    A1 Excavating and Drainage Inc 
$15,650.00 
    Larson Contracting Central LLC 
$21,342.10 
    Groves Contracting LLC 
$23,650.00 
    Pillar Inc. 
$24,800.00 


full bid tab