The following are the results of bids received January, 2018 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| BREMER -- PROJECT # 18-03-09-02 1/18/2018 Small Project Letting
| SWEET MARSH WMA
| RAILROAD DIKE REPAIR | | BIDS RECEIVED: |
Kinman Co Inc
|
$17,850.00 |
Matt Construction, Inc.
|
$18,400.00 |
Nate Moeller Construction LLC
|
$20,675.00 |
Donlon Brothers Construction LLC
|
$21,500.00 |
Lansing Brothers Const.
|
$23,300.00 |
Crane Construction
|
$24,550.00 |
Evergreen Lawn Care & Landscape LLC
|
$24,875.00 |
Chad Heim Excavating & Trucking LLC
|
$25,275.00 |
Cole Excavating, LLC
|
$34,250.00 |
Ray's Excavating, LLC
|
$49,000.00 |
|
| BREMER -- PROJECT # 18-03-09-03 1/18/2018 Small Project Letting
| SWEET MARSH WMA
| MEYER POND DIKE REPAIR | | BIDS RECEIVED: |
Crane Construction
|
$7,360.00 |
Lansing Brothers Construction
|
$9,900.00 |
Nate Moeller Construction LLC
|
$9,960.00 |
Sylvan Valley LLC
|
$10,469.00 |
Cole Excavating, LLC
|
$11,650.00 |
Kinman Co Inc
|
$13,000.00 |
Donlon Brothers Construction LLC
|
$14,400.00 |
Ray's Excavating, LLC
|
$15,000.00 |
Evergreen Lawn Care and Landscape LLC
|
$17,400.00 |
Chad Heim Excavating LLC
|
$19,690.00 |
Apex Companies, LLC
|
$22,885.80 |
|
| DICKINSON -- PROJECT # 18-01-30-03 1/18/2018 Small Project Letting
| GULL POINT LAW ENFORCEMENT
| STORAGE BUILDING RENOVATION | | BIDS RECEIVED: |
Cory Peters Construction
|
$44,691.61 |
3D Builders, LLC
|
$66,710.00 |
Wilcon Construction, Inc.
|
$76,689.00 |
Whetstone Building Services LLC
|
$87,500.00 |
Midstates Builders, Inc.
|
$103,530.00 |
|
| BREMER -- PROJECT # 18-03-09-04 1/25/2018 Small Project Letting
| SWEET MARSH WMA
| ALBRIGHT WETLAND DEVELOPMENT | | BIDS RECEIVED: |
Nate Moeller Const LLC
|
$89,937.90 |
Chad Heim Excavating & Trucking LLC
|
$91,387.30 |
Kinman Co Inc.
|
$91,471.06 |
David Ryan Construction
|
$94,744.98 |
Faas Construction & Excavating
|
$100,406.25 |
Blazek Corporation
|
$105,131.40 |
Steger Construction Inc.
|
$106,964.66 |
Walter Wenthold Excavating Inc
|
$116,745.85 |
Cole Excavating, LLC
|
$121,128.62 |
Crane Construction
|
$122,653.20 |
Matt Construction, Inc.
|
$127,882.20 |
Ethan Koehn Construction
|
$149,167.19 |
Ray's Excavating, LLC
|
$157,552.00 |
H&H Construction & Dev. LLC
|
$161,887.84 |
Mehmert Tiling, Inc.
|
$262,078.87 |
|
| SAC -- PROJECT # 18-01-81-02 1/25/2018 Small Project Letting
| BLACK HAWK LAKE
| ICE HOUSE POINT SHORELINE ARMOR | | BIDS RECEIVED: |
Richards Construction Co., Inc.
|
$24,050.00 |
L.A. Carlson Contracting, Inc.
|
$41,075.00 |
Flewelling Earthmoving Inc.
|
$53,575.00 |
|
|